Background

The original pipework system began to fail at the joints due to temperature-related stresses, resulting in severe leaks. In response, the client requested a full replacement of the existing system with PVC pipework.

Chemical Dosing System.jpg

Scope of Work – After Completion

The completed project involved the full installation of a PVC pipework system to support our client's process.

Lutz-Jesco Dosing 1

Project Breakdown

Project Design

Precision Arc Engineering was responsible for the complete design of the Sulphuric Acid dosing system. This included both internal and external layouts, encompassing all pipework, storage tanks, and instrumentation.

Screenshot 2025-07-29 162109.png

Fabrication

All pipework was fabricated in-house at our workshop. Site welding was conducted during installation, with all welds purged using high-purity argon to ensure cleanliness and prevent contamination.

7a69d8b6-ecf6-48d5-808a-0fcc41336850.png

Project Management

We provided comprehensive end-to-end project management, maintaining close collaboration with the client throughout each phase to ensure successful delivery.

 

360_F_472546867_4MBw9cVFYE7AwnrIIbmZ8xXS0V3mrIzr.jpg

Testing

​The sulphuric acid dosing system was rigorously tested to ensure reliable and accurate operation under expected field conditions. The testing process included calibration of the dosing pumps, verification of control logic, and leak checks across all pipework and containment areas.

pressure-testing-in-sept-800.png