The original pipework system began to fail at the joints due to temperature-related stresses, resulting in severe leaks. In response, the client requested a full replacement of the existing system with stainless steel pipework.

Project Design
Precision Arc Engineering was responsible for the complete design of the AdBlue mixing system. This included both internal and external layouts, encompassing all pipework, storage tanks, and instrumentation.

Fabrication
All pipework was fabricated in-house at our workshop. Site welding was conducted during installation, with all welds purged using high-purity argon to ensure cleanliness and prevent contamination.

Scope of Work – After Completion
The completed project involved the full installation of a stainless steel pipework system to support an AdBlue mixing process.

Project Management
We provided comprehensive end-to-end project management, maintaining close collaboration with the client throughout each phase to ensure successful delivery.

Installation
Acting as the principal contractor, Precision Arc Engineering managed all aspects of the installation. This included mechanical pipework, electrical systems, and civil works, ensuring seamless integration across disciplines.